| 2002 Street Improvement Bond Projects |
Status |
| South Corridor Transit Infrastructure (SCIP) |
|
| - New Bern/Marsh/South Blvd. Intersection |
Complete |
| - Rail Crossing Lane Streetscape |
Complete |
| - Remount/Ideal Way/South Blvd. Intersection |
Complete |
| - New Bern Sidewalk Package |
Complete |
| - Scaleybark Sidewalk Package |
Complete |
| - Woodlawn/Old Pineville Intersection |
Complete |
| - Woodlawn Sidewalk Package |
Complete |
| - Tyvola Intersection |
Complete |
| - Tyvola Sidewalk Package |
Complete |
| - Archdale Pedestrian/Bike/Intersection |
Complete |
| - Archdale Sidewalk Package |
Complete |
| - Arrowood Pedestrian/Bike/Intersection |
Complete |
| - Sharon Road West Intersection |
Complete |
| - Sharon Road West Sidewalk Package |
Complete |
| - Sharon Road West Pedestrian Bridge (Project to be re-bid) |
On Hold |
| - South Boulevard Sidewalks (Fill-In) |
Complete |
| - Old Pineville South Section |
Deferred |
| - Old Pineville Road North Section |
Construction |
| - Old Pineville Road Dewitt Extension (Freeland to Clanton) |
Construction |
| - Old Pineville Road Extension (to Arrowood Rd.) |
Deferred |
| - Woodlawn Bike Lanes (Murryhill to South Blvd.) |
Construction |
| - Multi-use trail (within Rail Right-of-Way) |
Construction |
| Hickory Grove Widening |
Complete |
| Third Street/Baldwin Intersection |
Complete |
| South Boulevard/Woodlawn Intersection |
Complete |
| |
|
| 2002 Road Planning/Design Projects |
Status |
| Rea Road Widening (Project to be placed On Hold) |
Design |
| Beatties Ford Road Widening (Capps Hill to Lakeview) |
On Hold |
| Idlewild Road Widening |
On Hold |
| Sugar Creek Road Widening (Coordinate with Transit Corridor) |
Planning |
| |
|
| 2004 Street Improvement Bonds |
Status |
| Fred D. Alexander Boulevard (Will be placed On Hold) |
Real Estate |
| Cindy Lane Extension |
Construction |
| Nevin Road Extension |
Construction |
| Dixie River Road Intersection |
Planning |
| |
|
| 2004 Neighborhood Bond Projects |
Status |
| Belmont-Segal Avenue Streetscape |
Design |
| Belmont-Gateways |
Design |
| Belmont-Pedestrian Improvements |
Design |
| |
|
| West Side Strategy Plan Projects |
Status |
| Brookshire Freeway Landscaping |
Complete |
| Morris Field Drive Widening |
Complete |
| West Boulevard Streetscape |
Complete |
| Wilkinson Boulevard Gateway |
Complete |
| Old Steele Creek Road Widening (Wingate NIP) |
Complete |
| Harlee/Stafford (On Hold until completion of CMU Main Project) |
On Hold |
| J.C. Smith Sidewalk |
Complete |
| West Morehead Streetscape |
Construction |
| Rozzelles Ferry Streetscape |
Real Estate |
| Statesville Avenue Streetscape |
Landscaping |
| Tuckaseegee Road Streetscape |
Construction |
| |
|
| Eastside Strategy Plan Projects |
Status |
| Norland Road Sidewalk |
Complete |
| Central Avenue Streetscape, phase 1 |
Complete |
| Central Avenue Streetscape, phase 2 |
Complete |
| Central Avenue Streetscape, phase 3 |
Complete |
| Albemarle Road Streetscape - Landscaping |
Complete |
| Pence Road Streetscape |
Complete |
| The Plaza Streetscape |
Complete |
| Eastland Mall Area Plan Study |
Complete |
| Central Avenue at Eastland Mall |
Design |
| |
|