EFFECTIVE JULY 27 - AUGUST 13, 2009
South Blvd/I-485 LYNX Station Park-and-Ride Work
LYNX Blue Line
Beginning Monday, July 27th, and lasting until Thursday, August 13th, contractors will be working at the LYNX Blue Line I-485 Park and Ride facility.
Starting on July 27th, work will be performed at the entry and exit lanes of the parking deck. Parking deck access will be reduced to one lane in the direction where the work is being performed, and only one lane will be closed at a time. Contractors will be working during the middle of the day, so customers may experience minimal delays during the morning or afternoon rush hour.
On August 3rd and 4th, contractors will be working in Lot A. Lot A is the recently opened surface lot, located in front of Texas Roadhouse.
Finishing work will take place on August 12th and 13th. Workers will be using ladders at the deck entrance and performing other activities in Lot A and at the road sign.
During these projects, any affected traffic patterns will be marked with safety cones. Customers should proceed with caution when entering and existing these work zones.