Business eServices Government Visitors Departments
 
Thomasboro-Hoskins, Phases 1, 2, 3 and 4

A 2000 Neighborhood Bond Project

The Thomasboro Hoskins project was divided into 4 phases and bid as four separate construction projects.  Morgan Street, Phase 1, was completed in February 2003.  Hoskins, Phase 2, was completed in March 2006.  Funds to build Glenwood, Phase 3 and Bradford, Phase 4 were included in the 2006 Transportation Bond Referendum approved by voters in November 2006. Glenwood, Phase 3, construction is expected to begin in 2010.

Objectives:

  • To construct infrastructure improvements including curb & gutter, planting strips, sidewalks, storm drainage, retaining walls, asphalt paving, sewer line upgrades, water line upgrades and landscaping
  • To design and install these NIP improvements in conjunction with the Blenhein CIP and the Westridge storm drainage project.

Click here to view the Phase 3 area map.

Click here to view the Phase 4 area map.

 
 


Thomasboro-Hoskins
This neighborhood project is funded through the 2000 and 2006 bond programs. Improvements will include curb & gutter, planting strips, sidewalks, storm drainage and sewer & water line upgrades, retaining walls, and landscaping.

What's happened?
Glenwood, Phase 3 - Real Estate Acquisition Phase is complete. Blythe Development was selected as the contractor.  Bradford, Phase 4 - A public meeting was held on June 2, 2009. 

What's next?
Glenwood, Phase 3 - Construction will begin in December 2009. Bradford, Phase 4 - Design Phase is underway and will extend through summer 2010.

Who to contact?
Kristie Kennedy, 704-336-6194.

 
 
Cost:  $9,300,000
Please note that this figure includes all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fees, construction, signalization, permits and landscaping.  
 
The Engineering and Property Management (E&PM) project team will manage the Thomasboro Hoskins Neighborhood Improvement Project through a four stage process.  Specific work is conducted during each stage with an emphasis on public involvement during the planning and design phases.  Click here  to learn how City projects are selected, designed and built.

Project Contacts:
Kristie Kennedy, Engineering Project Manager, 704-336-6194
Chad Nussman, Storm Water Project Manager, 704-336-5676
Cheryl Rance, Neighborhood Development, 704-353-1235