Upcoming Construction Projects
In addition to the CLT 2015 development program, there are other projects at various stages of implementation. When complete, CLT will look very different than it does today and use more modern and efficient technology to meet customers’ needs and expectations.

As these projects become active, they will be added to the main construction page.

Business Valet Deck II

Airfield:
Terminal Ramp Expansion (West) I

Concourse Expansions:
Concourse A Annex
Concourse B
Concourse E

Business Valet Deck II
Status: Under Design
Description: Due to the popularity of CLT’s Business Valet services and forecasted passenger growth, a second Business Valet Parking Deck will be built. The deck will be located on the west side of the existing Business Valet Deck along Wilkinson Boulevard.

Land clearing began in summer 2012. Grading for the 3,200-space deck is complete and construction will commence in June.
Duration: 12 months
Milestones:

Bid Opening May 2013
Award Contract June 2013
Construction July 2013 – June 2014
Operational June 2014

Cost: $50,000,000
Funding Source: 2013 GARBS

 


Terminal Ramp Expansion (West) I
Status: Preliminary Engineering Underway
Description: This project will design and construct an additional aircraft ramp that will accommodate a future four-gate concourse (Concourse A North Expansion).
The ramp expansion project responds to the demand for increased aviation activity and additional air service to the region over time.
Duration: 14 months
Milestones: Design March – June 2013
Advertise for bids July 2013
Award contract August 2013
Construction August 2013 – October 2014
Cost: $7,000,000
Funding Source: 2013 GARBS
Federal AIP Grant



Concourse A Annex
Status: Planned
Description: This project plans for the construction of four additional gates north of Concourse A and will accommodate expanding air service.
Duration: 9 months
Milestones: Design April – October 2013
Advertise for bids November 2013
Award contract December 2013
Construction January – September 2014
Cost: $18,000,000
Funding Source: 2013 GARBS



Concourse B
Status: Planned
Description: This project will provide for design and construction of an additional 10 gates on Concourse B.
Duration: 31 months
Milestones: Design April – October 2013
Advertise for bids November 2013
Award contract December 2013
Construction January 2014 – July 2016
Cost: $70,000,000
Funding Source: 2013 GARBS



Concourse E
Status: Planned
Description: This project will add up to six gates for a total of up to 42. The project will also add jet bridges to the remaining gates.
Duration: 14 months
Milestones: Design April – September 2013
Advertise for bids October 2013
Award contract November 2013
Construction January 2014 – March 2015
Cost: $34,112,500
Funding Source: 2013 GARBS