This project will improve the drainage system near Central Avenue.

What's happened? The project team has completed the design for the upgraded drainage. Property owners affected by the pending construction have been contacted and the necessary easements acquired. In December, City Council awarded the construction contract.

What's next? The bid phase is complete. Construction will begin in March and should be complete by June.

Who to contact? Keith Carpenter, 704-336-3650
This project involves drainage improvements related to the Central Avenue Streetscape project. These improvements to the undersized downstream system are necessary because of upgrades made to the Central Avenue drainage system.  The existing system will be brought up to current standards beginning a the Central/Medford intersection and ending at a point of discharge across Eastway Drive and north of Central Avenue.

Cost:  $800,000
Please note this is the funding amount and includes all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fees, construction, signalization, permits and landscaping.  Additional funding may be identified after the planning phase.

The Engineering & Property Management (E&PM) project team will manage the Eastway-Medford Storm Drainage Improvement  Project through a four stage process. 

Project Contacts:
Keith Carpenter, Engineering Project Manager, 704-336-3650