Edgewood Neighborhood Improvement Project

Edgewood
The Edgewood neighborhood will receive infrastructure improvements such as new curb and gutter, sidewalks and storm drainage.

What's happened? City staff worked with Armstrong Glen, Inc., the consultant/designer to plan and design the improvements for the Edgewood Neighborhood. All property acquisition was complete in January, 2007.  Bids were received and a construction contract was awarded to Ferebee. Construction began in June.

What's next?  Construction continues and should be complete by October, 2008.

Who to contact:  Leslie Bing, 704-336-7277

A 2000 Neighborhood Bond Project

This neighborhood improvement project will construct curb and gutter, sidewalk, and minor storm drainage. These improvements will be installed on portions of Marlene Street, Susan Street, Cheshire Avenue, Santee Street, Browning Avenue, Thriftwood Drive and Lawrence Street.

Objectives:

  • Maintain, stabilize and revitalize the neighborhood through comprehensive infrastructure improvements
  • Strengthen the neighborhood and surrounding community
  • Finish the project below budgeted construction costs
Cost:  $2,000,000
Please note that this figure includes all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fees, construction, signalization, permits and landscaping.  
 
The Engineering and Property Management (E&PM) project team will manage the Edgewood Neighborhood Improvement Project through a four stage process. Specific work is conducted during each stage with an emphasis on public involvement during the planning and design phases. Click here to learn how City projects are selected, designed and built. 

Project Contacts:
Leslie Bing, E&PM Project Manager, 704-336-7277