Freedom Drive
This project will widen Freedom Drive to four lanes from Edgewood Road to Toddville Road.
What's happened? City Council awarded the construction contract to Blythe Construction in January 2012 and construction began April 2, 2012.
What's next? Construction began in April 2012 and is 45% complete. The contractor, Blythe Construction has completed installing new asphalt pavement, storm drain pipe, and most of the sidewalk and curb & gutter along the eastbound travel lanes of Freedom Drive from Toddville to Edgewood/Bradford. This is done in order to shift traffic to the south side of Freedom Drive, currently scheduled for Saturday, April 20, 2013. Upon shifting the traffic, the contractor will begin construction on the north side of Freedom. Construction should be complete by fall 2014.
Click here to view March 2011 newsletter.
Click here to view the March 2012 newsletter.
Click here to view the April 2013 newsletter.
Who to contact: Geen Cheng Khoo, 704-336-4492