Home
Storm Water Projects
Drainage & Flooding
Pollution Prevention
Fees & Billing
Volunteer
Storm Water A-Z
Print this PageSite Feedback
Cherokee/Scotland Storm Drainage Improvement Project
The Cherokee/Scotland Storm Drainage Improvement Project will improve the storm drainage infrastructure in order to reduce flooding of streets, properties and structures.  Streams will also be stabilized and/or restored in order to provide a more natural, stable stream system throughout the area.  The project is currently in the Design Phase.
Objectives:

- Reduce structure and street flooding throughout the neighborhood.

- Address channel erosion problems within the project area.

Cost:  To Be Determined
Please note that this figure includes all costs associated with the project such as planning and design, utility relocation, consultant fees, construction, permits and landscaping.
 Cherokee/Scotland Project Area Map
The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage the Cherokee/Scotland Project through the phases listed below.

A general description and range of typical timeframes for project phases is given below.  Specific work is conducted during each phase while an emphasis is made on public involvement throughout the entire project.

Planning Phase (July 2003 to December 2008)
During the planning phase, questionnaires and public meetings are used to obtain input from property owners. Several improvement alternatives are developed and evaluated to determine the best solution. A recommended alternative is presented to the public for comment at the end of the planning phase. Although the planning phase of a project typically would last from 12 to 27 months, changes in the project team have delayed the planning phase of the project. As of March 2005, a new consultant is analyzing the existing conditions of the storm water system within the project area. Once this evaluation is complete, there will be a public meeting to present the findings to the neighborhood and to receive feedback on these findings.

Design Phase (January 2009-Spring 2012)
During the design phase, construction drawings for the alternative selected during the planning phase are developed.  Many details must be addressed including the determination of specific pipe sizes and alignments, channel widths and lining types, inlet sizes and locations, utility relocations, and easement locations.  The design phase of a project typically lasts 21 to 34 months.  Due to additional storm drainage system added to the project, revisions in the design have taken place and extended the original schedule.

Permitting Phase (January 2011)
During the permitting phase, the required water quality permits are obtained from Federal and State governments.  Other permits such as permission to work within railroad and NCDOT rights-of-way will be obtained during this phase.  The permitting phase of a project typically lasts 3 to 9 months.  The permitting phase of a project may overlap other phases.

Property Easement/Acquisition (October 2011)
The City's real estate staff works with citizens and businesses to acquire Storm Drainage Easements (SDEs).  The City requests that SDEs be donated to provide access to your property to make the recommended improvements and provide future maintenance.  In addition to SDEs, temporary construction easements may be needed to access work areas.  The bid phase will begin after all easements are acquired.  The easement acquisition phase of a project typically lasts 8 to 12 months.

Bid Phase (Spring 2014)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process.  By state law, the lowest responsible bidder is awarded the construction contract.  The bid phase of a project typically lasts 4 to 5 months.

Construction Phase (Fall 2014)
Throughout construction, efforts will be made to minimize disruption to nearby property owners.  Construction of proposed improvements will be supervised by City inspectors.  Notifications of key construction dates and will be mailed to residents prior to construction.  Because projects vary in size, the typical construction phase of a project can last from 3 months to over 2 years.

Project Team

Jackie Bray
City Project Manager
704-336-6770

Harold Smith
City Project Coordinator
704-432-5532

Doug Lozner, P.E.
Watershed Area Manager
704-432-0964

Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183

Newsletters

February 2014 
October 2013
June 2013
February 2013
October 2012
June 2012
February 2012
October 2011
June 2011
February 2011
January 2011
October 2010
June 2010
February 2010
October 2009
June 2009
February 2009
October 2008
June 2008
Project Survey

Meeting Minutes  

Updated Exhibits - October 5, 2011

        Updated Design Exhibit - Bolling Road (3.92 MB)
        Updated Design Exhibit - Scotland Ave Bypass (1.77 MB)
        Updated Design Exhibit - Floodplain Bench Area (2.01 MB)
        Updated Design Exhibit - Northern Section (8.82 MB)
        Updated Design Exhibit - Southern Section (7.44 MB)

January 20, 2011 

May 8, 2008

October 25, 2005