|
First Ward Storm Drainage Improvement Project
|
|
The First Ward Storm Drainage Improvement Project (SDIP) will improve the storm drainage infrastructure in order to reduce flooding of streets, properties and structures. First Ward SDIP consists of the main storm water system that starts at the intersection of East 8th Street and North Caldwell Street and discharges into a channel near the intersection of North McDowell Street and East 6th Street. The project area encompasses a drainage area of approximately 163 acres of Uptown Charlotte and is shown below.
Storm Water Services has a standard questionnaire for property owners to provide their input and concerns. This information is being utilized during the design phase to provide solutions to current drainage issues. If you are experiencing drainage issues on your property that have not been reported in the previous questionnaire(s) please take the time to complete a questionnaire. It is the intent of this project to reduce flooding of streets, properties and structures along the main storm water system corridor when it is constructed.
|
|
Please check back periodically for informational updates.
Objectives:
- Reduce structure flooding within the project area.
- Reduce street flooding within the project area.
Cost: To Be Determined (TBD)
Please note that this figure will include all costs associated with this project such as planning and design, utility relocation, consultant fees, construction, necessary permitting and landscaping. |
|
|
|
|
The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage First Ward SDIP through the phases listed below. A general description and range of typical timeframes for project phases is given below. Specific work is conducted during each phase while an emphasis is made on public involvement throughout the entire project. Public meetings will be held throughout the project with the affected property owners to present the planning and design information and receive input.
Planning Phase (August 2011 – TBD)
During the planning phase, citizen and public meetings are used to obtain input from property owners and residents. Several improvement alternatives are developed and evaluated to determine the best solution. A recommended alternative is presented to the public for comment at the end of the planning phase. The planning phase of a project typically lasts 12 to 27 months. Due to some preliminary analysis already being completed prior to the start of planning, the planning phase for the First Ward SDIP is expected to last 4 to 12 months.
Design Phase (Time frame TBD)
During the design phase, construction drawings are developed for the alternative selected during the planning phase. Many details must be addressed including the determination of storm drainage pipe sizes and alignments, utility relocations, easement locations, and traffic control logistics. The design phase of a project typically lasts 21 to 34 months. Due to an accelerated schedule on this project we expect the design phase to last 12 to 24 months.
Permitting Phase (Time frame TBD)
During the permitting phase, the required water quality permits are obtained from Federal and State governments. Other permits such as permission to work within railroad and NCDOT rights-of-way may also be obtained during this phase if necessary. The permitting phase of a project typically lasts 3 to 9 months; however, it may overlap other phases.
Property Easement/Acquisition (Time frame TBD)
The City's real estate staff works with citizens and businesses to acquire either Conservation Easements or Storm Drainage Easements. In addition, temporary construction easements may also be needed to access work areas. The City requests that easements be donated to provide access to your property to make the recommended improvements and provide future maintenance. The easement acquisition phase of a project typically lasts 8 to 12 months.
Bid Phase (Time frame TBD)
The bid phase will begin after all required permits are obtained and all easements are acquired. During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process. By state law, the lowest responsible bidder is awarded the construction contract. The bid phase of a project typically lasts 4 to 5 months.
Construction Phase (Time frame TBD)
Throughout construction, efforts will be made to minimize disruption to nearby property owners. Construction of proposed improvements will be supervised by City inspectors. Notifications of key construction dates will be mailed to residents prior to construction. Because projects vary in size, the typical construction phase of a project can last from 3 months to over 2 years.
Project Team
David T. Baker, P.E.
City Project Manager
704-432-5569
Kate Labadorf, P.E.
City Project Manager
704-336-3653
Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183
Newsletters
April 2012
December 2011
August 2011 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|