View a larger map of the proposed project improvement area
Design Phase (Completed January 2009)
During the design phase, construction drawings for the alternative selected during the planning phase are developed. Many details must be addressed including the determination of specific pipe sizes and alignments, channel widths and lining types, inlet sizes and locations, utility relocations, and easement locations. The design phase of a project typically lasts 21 to 34 months.
Permitting Phase (Completed October 2008)
During the permitting phase, the required water quality permits are obtained from Federal and State governments. Other permits such as permission to work within railroad and NCDOT rights-of-way will be obtained during this phase. The permitting phase of a project typically lasts 3 to 9 months. The permitting phase of a project may overlap other phases.
Property Easement/Acquisition (Completed February 2009)
The City's real estate staff works with citizens and businesses to acquire Storm Drainage Easements (SDEs), and Conservation Easements (CEs). The City requests that SDEs and CEs be donated to provide access to your property to make the recommended improvements and provide future maintenance. In addition to SDEs, temporary construction easements may be needed to access work areas. The bid phase will begin after all easements are acquired. The easement acquisition phase of a project typically lasts 8 to 12 months.
If you have any questions about easement acquisition, please contact Julie Millea, City Real Estate Agent, 704-336-3104.
Bid Phase (Completed June 2009)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process. By state law, the lowest responsible bidder is awarded the construction contract. The bid phase of a project typically lasts 4 to 5 months.
Construction Phase (Completed October 2010)
Throughout construction, efforts will be made to minimize disruption to nearby property owners. Construction of proposed improvements will be supervised by City inspectors. Notifications of key construction dates and will be mailed to residents prior to construction.
Project construction was substantially complete in October 2010. The contractor has since addressed all punch list items and installed all vegetation. The Reddman Road cul-de-sac will be resurfaced by fall of 2011.
Project Team
Jennifer Barker, P.E.
City Project Manager
704-432-0963
Doug Lozner, P.E.
Watershed Area Manager
704-432-0964
Gary Stansbury
City Construction Manager
704-336-2667
Donna Bost
City Construction Inspector
704-400-1987
Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183
Newsletters
June 2010
February 2010
June 2009
June 2008
October 2007
Meeting Minutes
May 7, 2008
September 28, 2006