Home
Storm Water Projects
Drainage & Flooding
Pollution Prevention
Fees & Billing
Volunteer
Storm Water A-Z
Print this PageSite Feedback
Parkwood Phase 1 Storm Drainage Improvement Project
​​​​
The Parkwood Phase 1 Storm Drainage Improvement Project is roughly bordered by the railroad tracks that run parallel to North Tryon Street (between North Tryon and Brevard) on the northwest, I-277/Brookshire Freeway on the southwest, Little Sugar Creek (or N. Myers Street) on the southeast, and E. 18th Street on the northeast.

Phase 2

Objectives:
- Reduce structure and street flooding throughout the neighborhood.
- Address channel erosion problems within the project area.

Parkwood Phase I project area map 

Estimated Cost:  $9,100,000
Please note that this figure includes all costs associated with the project such as planning and design, utility relocation, consultant fees, construction, permits and landscaping.

The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage the Parkwood Storm Drainage Improvement Project through the phases listed below. A general description and range of typical timeframes for project phases is given below. Specific work is conducted during each phase while an emphasis is made on public involvement throughout the entire project.  Public meetings were held with the affected property owners to present the planning and design information and receive input.

Planning Phase (November 2010 – January 2012)
During the planning phase, public meetings are used to obtain input from property owners. Several improvement alternatives are developed and evaluated to determine the best solution. A recommended alternative is presented to the public for comment at the end of the planning phase. The planning phase of a project typically lasts 12 to 27 months.

Design Phase (January 2012 - December 2013)
During the design phase, construction drawings are developed for the alternative selected during the planning phase. Many details must be addressed including the determination of channel widths and lining types, utility relocations, and easement locations. The design phase of a project typically lasts 21 to 34 months.

Permitting Phase (December 2012 - September 2013)
During the permitting phase, the required water quality permits are obtained from Federal and State governments. Other permits such as permission to work within railroad and NCDOT rights-of-way may also be obtained during this phase if necessary. The permitting phase of a project typically lasts 3 to 9 months; however, it may overlap other phases.

Property Easement/Acquisition (March 2013 - January 2014)
The City's real estate staff works with citizens and businesses to acquire either Conservation Easements or Storm Drainage Easements. In addition, temporary construction easements may also be needed to access work areas. The City requests that easements be donated to provide access to your property to make the recommended improvements and provide future maintenance. The bid phase will begin after all easements are acquired. The easement acquisition phase of a project typically lasts 8 to 12 months.

Bid Phase (December 2013 - May 2014)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process. By state law, the lowest responsible bidder is awarded the construction contract. The bid phase of a project typically lasts 5 to 6 months.

Construction Phase (End by Winter 2016)
Throughout construction, efforts will be made to minimize disruption to nearby property owners. Construction of proposed improvements will be supervised by City inspectors. Notifications of key construction dates will be mailed to residents prior to construction. The construction phase of this project can last up to 2 years.

Project Team:

Adam Clapp
City Construction Inspector
704-400-2006

Steve Canter
Construction Supervisor
704-336-7047

David N. Perry, P.E.
City Project Manager
704-336-4202

Amy Bice, E.I.
Watershed Area Manager
704-432-0965

Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183

Newsletters

May 2014 
January 2014 
September 2013
May 2013
April 2013
February 2013
October 2012
June 2012
February 10, 2012
February 2012
December 2011
August 2011
June 2011
February 2011