|
Peterson Drive Storm Drainage Improvement Project
|
Image1
|
|
Content1 The Peterson Drive Storm Drainage Improvement Project will reduce flooding of streets and properties by improving roadway crossings, pipe systems, and stream channels. Stream banks will be stabilized to minimize erosion through improvements to the channel shape and through the use of selected plantings.
Objectives: - Reduce flooding at Heriot Ave., Sarah Drive, and Stuart Andrew Boulevard and nearby properties by upgrading roadway crossings, underground pipe systems and channels. - Minimize erosion along the receiving stream by improving the channel cross-section and alignment. |
 |
Estimated Cost: $ 6,000,000 Please note that this figure includes all costs associated with the project such as planning and design, utility relocation, consultant fees, construction, permits and landscaping. The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage the Peterson Project through the phases listed below.
|
|
|
|
Content2
|
Content3
|
|
Content4
|
Content5
|
|
|
Content6 Design Phase (Completed) During the design phase, construction drawings for the alternative selected during the planning phase are developed. Many details must be addressed including the determination of specific pipe sizes and alignments, channel widths and lining types, inlet sizes and locations, utility relocations, and easement locations. The design phase of a project typically lasts 21 to 34 months.
Property Easement/Acquisition (Started September 2011) The City's real estate staff works with citizens and businesses to acquire Storm Drainage Easements (SDEs). The City requests that SDEs be donated to provide access to your property to make the recommended improvements and provide future maintenance. In addition to SDEs, temporary construction easements may be needed to access work areas. The bid phase will begin after all easements are acquired. The easement acquisition phase of a project typically lasts 8 to 12 months.
Permitting Phase (Time frame TBD) During the permitting phase, the required water quality permits are obtained from Federal and State governments. Other permits such as permission to work within railroad and NCDOT rights-of-way will be obtained during this phase. The permitting phase of a project typically lasts 3 to 9 months. The permitting phase of a project may overlap other phases.
Bid Phase (Time frame TBD) During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process. By state law, the lowest responsible bidder is awarded the construction contract. The bid phase of a project typically lasts 4 to 5 months.
Construction Phase (Time frame TBD) Throughout construction, efforts will be made to minimize disruption to nearby property owners. Construction of proposed improvements will be supervised by City inspectors. Notifications of key construction dates and will be mailed to residents prior to construction. Because projects vary in size, the typical construction phase of a project can last from 3 months to over 2 years.
Project Team
Brant Smiley City Project Manager 704-432-2147
Amy Bice, E.I. Watershed Area Manager 704-432-0965
Matthew Gustis, P.E. City Engineering Team Program Manager 704-336-6183
Newsletters
April 2013 December 2012 August 2012 April 2012 November 2011 October 2011
|
|
|
|
Content7
|
Content8
|
|
Content9
|
Content10
|
|
|
Content11
|
|
|