- Reduce structure and street flooding throughout the neighborhood.
- Address channel erosion problems within the project area.
Cost: $7,200,000
Please note that this figure includes all costs associated with the project such as planning and design, utility relocation, consultant fees, construction, permits and landscaping.
The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage the Wiseman Storm Drainage Project through the phases listed below. A general description and range of typical timeframes for project phases is given below. Specific work is conducted during each phase while an emphasis is made on public involvement throughout the entire project. Public meetings have been and will continue to be held throughout the project with the affected property owners to present the planning and design information and receive input.
Planning Phase (March 2009 - November 2010)
During the planning phase, public meetings are used to obtain input from property owners. Several improvement alternatives are developed and evaluated to determine the best solution. A recommended alternative is presented to the public for comment at the end of the planning phase. The planning phase of a project typically lasts 12 to 27 months.
Design Phase (December 2010 - TBD)
During the design phase, construction drawings are developed for the alternative selected during the planning phase. Many details must be addressed including the determination of pipe locations, channel widths, utility relocations, and easement locations. The design phase of a project typically lasts 21 to 34 months.
Permitting Phase (April 2012 - TBD)
During the permitting phase, the required water quality permits are obtained from Federal and State governments. Other permits such as permission to work within railroad and NCDOT rights-of-way may also be obtained during this phase if necessary. The permitting phase of a project typically lasts 3 to 9 months; however, it may overlap other phases.
Property Easement/Acquisition (September 2011 - TBD)
The City's real estate staff works with citizens and businesses to acquire either Conservation Easements or Storm Drainage Easements. In addition, temporary construction easements may also be needed to access work areas. The City requests that easements be donated to provide access to your property to make the recommended improvements and provide future maintenance. The bid phase will begin after all easements are acquired. The easement acquisition phase of a project typically lasts 8 to 12 months.
Bid Phase (Time frame TBD)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process. By state law, the lowest responsible bidder is awarded the construction contract. The bid phase of a project typically lasts 4 to 5 months.
Construction Phase (Time frame TBD)
Throughout construction, efforts will be made to minimize disruption to nearby property owners. Construction of proposed improvements will be supervised by City inspectors. Notifications of key construction dates will be mailed to residents prior to construction. Because projects vary in size, the typical construction phase of a project can last from 3 months to over 2 years.
Project Team
Jackie Bray
City Project Manager
704-336-6770
Amy Bice, E.I.
Watershed Area Manager
704-432-0965
Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183
Newsletters
February 2013
October 2012
June 2012
February 2012
October 2011
July 2011
March 2011
November 2010
August 2010
April 2010
December 2009
Meeting Minutes
September 21, 2011
Exhibit Overview Map
Exhibit Overview Aerial Map
October 6, 2010
Overview Map/Exhibit 11x17
Overview Map/Exhibit 24x36
Stream Stabilization Reach 4
Stream Stabilization Reach 5
Sunflower Road Culvert
Valley Grove Road Culvert
Arrow Lane Closed System
Braewick Place Culvert
Cross Winds Road Culvert
Mission Hills Road Culvert
July 21, 2009
Exhibit